Client: First Energy
Location: Eastlake, OH

As one of STEVENS many power clients, First Energy desires to upgrade a coal handling system from a rotary dump type to a rapid discharge. This project includes engineering and installation of all transfer conveyors and drives, and converted process control scheme to PLC control security. This upgrade increases their capacity from 2,500 ton per hour to 4,000 ton per hour.

STEVENS’ services for the project include project management, construction engineering, automation, electrical installation, and start-up services. The prime contractor for this project is the STEVENS construction team. Total project cost is $ 15 million.